Solar-LIT’s 2,017 PV Cleaning Robots Pass Reliability Acceptance at Saudi Arabia’s Haden Project


Release time: 2026-11-11 11:22:25.000

PROJECT CASE / SAUDI ARABIA

Solar-LIT Passes Reliability Acceptance at Haden with 2,017 PV Cleaning Robots

2,017 robots · 130 days to acceptance · 14 valid test days

Solar-LIT has completed reliability acceptance for 2,017 fully automated PV cleaning robots deployed in the North Section of the Haden 2 GW solar project in Saudi Arabia. The deployment progressed from robot installation and system commissioning to Reliability Run Test (RRT) acceptance in 130 days.

Reliability verification conducted between 20 September and 4 October 2026 covered 14 valid test days. The reported results were 99.99% robot availability and 99.87% overall availability, demonstrating stable operation within the project’s defined test period.

Haden 2 GW solar project in Saudi Arabia

Haden 2 GW solar project in Saudi Arabia

Project at a Glance

LocationMakkah Province, Saudi Arabia
Project capacity2 GW for the Haden project as a whole
Solar-LIT scopePV cleaning robots and management system for the North Section
Robots deployed2,017
Installation to acceptance130 days
Verification period20 September–4 October 2026; 14 valid test days

From Installation to RRT Acceptance in 130 Days

The Haden project forms part of Saudi Arabia’s national renewable energy programme and is being built under an EPC contract by a consortium of China Energy Engineering Group (CEEC) companies.

Solar-LIT supplied the North Section’s intelligent cleaning robots and associated management system to support automated cleaning and photovoltaic operations and maintenance (O&M).

Working in the desert’s high temperatures and wind-blown sand, Solar-LIT’s delivery and technical teams coordinated on site with the CEEC consortium on equipment deployment, integrated commissioning and customer training.

The process from mounting the robots on the arrays to RRT acceptance took 130 days. No quality complaints were recorded during project implementation, testing and acceptance.

PV cleaning robots deployed in the North Section of the Haden project

Coordinated Fleet Operation on 1P Single-Axis Trackers

The project uses 1P horizontal single-axis trackers. Changing module angles create additional demands on robot alignment and stable travel.

Solar-LIT’s robots use intelligent braking and multi-sensor fusion for posture correction. The system corrects deviation and returns the robot to alignment within five seconds, supporting stable travel under dynamic tracking conditions.

Communication gateways and Solar-LIT’s proprietary SCADA management platform provide status monitoring and remote dispatch for all 2,017 robots, supporting coordinated operation across the fleet.

O&M personnel inspecting cleaning equipment at the Haden project

Reliability Verified Across 14 Valid Test Days

Sustained operation is a critical test once a large robot fleet has been deployed. Between 20 September and 4 October 2026, the project’s North Section completed reliability verification covering 14 valid test days.

Robot availability99.99%
Overall availability99.87%

These are separate availability measures reported for this verification exercise in the North Section.

The completed deployment and reliability acceptance demonstrate Solar-LIT’s capabilities in product reliability, system integration and overseas project delivery.

Supporting Intelligent Solar O&M

As Saudi Arabia advances its Vision 2030 agenda and energy transition, intelligent equipment and engineering delivery capabilities are supporting the development of large-scale renewable energy projects.

Solar-LIT will continue to develop robotic technologies that support intelligent cleaning and O&M across the global solar industry.

More news

Solar-LIT’s 2,017 PV Cleaning Robots Pass Reliability Acceptance at Saudi Arabia’s Haden Project

Solar-LIT’s 2,017 PV cleaning robots passed reliability acceptance at Haden North, with 99.99% robot availability across 14 valid test days.

Solar Cleaning & Installation Robots at REI 2026 | Solar-Lit

At REI 2026 in Greater Noida, Solar-Lit presented three solar robotics categories and discussed site compatibility, construction coordination and long-term O&M.

Solar-LIT Showcases Intelligent PV Robotics at CIFIT 2026, Advancing China-Saudi Green Energy Cooperation

Solar-LIT showcased intelligent PV robotics and lifecycle solutions at CIFIT 2026 in Xiamen, strengthening China-Saudi cooperation in solar energy, PV installation and intelligent O&M.

Solar-LIT Intelligent PV Module Installation Robot Records 124.7 Modules per Hour in Xinjiang Field Test

A six-person site crew and the Solar-LIT system installed 212 PV modules in 102 minutes across six consecutive work batches at the Ruoqiang demonstration site.